Projects Status
August 23, 2010
-
Middlebelt Road from 8 Mile to 11
Mile – The Road Commission for Oakland County is
resurfacing the existing pavement as well as adding minor
improvements. The project will be completed in two phases.
Phase I, which includes all work between 8 Mile Road and 10
Mile Road, is substantially complete. Phase II, which includes
all work between 10 Mile Road and 11 Mile Road, is underway
and on schedule to be substantially complete by August 30.
Initial work in Phase II includes, but is not limited to,
excavation for widening, utility work, signal work and
removals. Middlebelt Road will be open to traffic during
construction but expect delays.
-
Inkster Road from 9 Mile to 11 Mile
– The City of Southfield is reconstructing the existing
roadway in two phases. Phase I, which includes all work
between 10 Mile Road and 11 Mile Road, is substantially
complete. Phase II is underway and will continue well into
October. During Phase II Inkster Road will be closed from 9
Mile Road to 10 Mile Road and traffic will be detoured east to
Beech Road.
-
Orchard Lake Road from 12 Mile to 13
Mile – The Road Commission for Oakland County is
nearing completion of this project. Remaining work includes
landscape restoration which will be done with short term lane
closures.
-
Grand River Avenue from Ten Mile
Road to Haggerty Road – Reconstruction of the
existing road is underway. Current work includes new curb,
drive approaches, utility work and grade preparation for the
new pavement. Travel is reduced to one lane in each direction.
Grand River will be open to traffic with the exception of a
short term weekend closure of the bridge over I-275 that is
currently scheduled for the weekend of September 11th. Closure
dates will be posted on site using portable message boards a
minimum of seven days in advance of the work. The suggested
detour route uses Haggerty and 10 Mile Roads.
-
Woodbine Subdivision
- the base pavement is complete in Phase I and
excavation on Phase II is currently underway. This project is
on schedule for completion in late September.
-
Hunters Pointe Subdivision
- The base pavement course is complete in Phase I and is
currently being installed in Phase II. Paving of the final
course of asphalt will start next week and is scheduled to be
substantially complete by September 3rd, restoration work will
follow.
-
M-5 Ramp from northbound M-5 to
westbound I-96 – MDOT currently has this ramp closed
for bridge reconstruction until late September.
-
I-96 from Novi Road to east of Beck
Road – MDOT is scheduled to have the left lane closed
of east bound I-96 from 7:00 AM to 7:00 PM on August 21 to
move traffic from the east bound lanes to the west bound
lanes.
-
I-96 east bound exit ramp to Novi
Road – MDOT is scheduled to have this ramp closed
from 9:00 AM on August 24 until 5:00 PM on October 31 for ramp
reconstruction.
To receive emails from the City regarding road construction
projects, click here.
All project dates are tentative pending weather conditions and
contractor schedules.
Click
here to view a map of current construction projects in the city.
If you have any questions about current construction
projects, please call the Engineering Division at (248)
871-2560.
For more info about MDOT projects,
visit
the MDOT website, and click on Major Projects under
Construction.
|

|